09 February 2017 by Chris Anderson, Director
A construction contractor can apply to a Local Authority (LA) for ‘prior consent’ for works under Section 61 of the Control of Pollution Act 1974 by submitting, in advance, details of the proposed work and the expected impact of noise and vibration on nearby sensitive receptors. The application typically involves completing the sections within a standard form supplied by the LA with details of proposed working hours, equipment to be used and predicted noise levels at sensitive locations. Supporting information (e.g. stand-alone noise and vibration reports or calculations etc.) can be attached.

Figure 1: Excerpt from a typical Section 61 Application Form
This type of application is often used when it is likely that the works will cause disturbance to residents but the contractor is willing to take the initiative in discussing the issues with the Local Authority and to establish the best practical means (BPM) for minimising intrusive noise and vibration. The alternative is that the Local Authority can use Section 60 of the Control of Pollution Act to impose its own criteria on the contractor, which may be more restrictive and therefore more likely to result in work being stopped or delayed if those criteria are exceeded.
Railway infrastructure projects (e.g. bridge replacements) often make use of Section 61 consents since the work will often involve heavy machinery and noisy activities close to residences. Further to this, whilst work is generally undertaken during the day where possible, any activities that require the cessation of rail traffic (where the contractor has to take ‘possession’ of the line) will generally be undertaken during the sensitive night-time and bank-holiday periods in order to minimise disruption to the transport system.
All of the above factors mean that the impact of noise and vibration is typically a major concern to the LA during such works and that it is therefore in the interests of the contractor to demonstrate that their responsibilities regarding noise and vibration mitigation are being taken seriously.
Figure 2: Bridge replacement works underway with housing nearby
The benefit of a Section 61 Consent to the contractor is that permission for the work is given in advance and, provided the consent remains in force and the terms of the consent are met throughout the works, a local authority cannot then take action under Section 60 of the Control of Pollution Act 1974 or Section 80 of the Environmental Protection Act 1990. A Section 61 consent can also be used in an appeal against a noise abatement notice, but compliance with the consent does not mean that nuisance action cannot be taken under Section 82 of the Environmental Protection Act 1990 or under common law.
A Section 61 Application must be submitted at least 28 days prior to commencement of work since this is the allocated time frame within which the LA must respond.
Spectrum would recommend that typically 4-8 weeks should be allowed for the preparation of the Section 61 Application since a significant amount of information and noise prediction work may be required, as described below.
The following table summarises the information and activities typically required in the preparation of a Section 61 Application :-
Table 1: List of information typically required to complete a Section 61 Application

Figure 3: Noise logging equipment at a secure location

Figure 4: Temporary acoustic barriers are one of several noise mitigation measures recommended for consideration in BS5228
Predicted levels can be provided numerically but also as noise contours for each phase of the works. Noise contours provide an instantaneous visual indication of the area that will be affected by noise from the works and are therefore often favoured by the LA.
Figure 4: Noise Contour Map showing predicted noise levels during part of a bridge replacement project

Figure 5: Graphical representation of measured environmental noise levels

Further information on Environmental Noise & Vibration Measurement